Project Name:
Illinois Tollway Roadway Resurfacing and Bridge Repairs
Start/Scheduled Date of Completion:
March 2018 - November 2020
SQN's Role on Project:
Field Engineering
Project Scope:
The overall project is for the roadway and bridge rehabilitation of 7 mainline bridges and culverts and 9 crossroad bridges along the Reagan Memorial Tollway (I-88) between IL Route 251 (milepost 76.1) and Annie Glidden Road (milepost 91.4), a 15 mile section. The work includes shoulder reconstruction, pavement patching, reconstruction and rehabilitation of ramps, installation of guardrail, median barrier and median pier protection, signs, lighting, drainage, pavement markings, erosion control and landscaping. The roadway resurfacing portion of the work was completed in 2018.
Total Project Budget:
$48,560,404.00
Project Delivery Method:
Design/Bid/Build
Prime/Subcontractor:
Subcontractor