Project Name:
CTA Illinois Medical District Station Renovation Project
Start/Scheduled Date of Completion:
September 2016 - August 2018
SQN's Role on Project:
Safety Manager / Field Engineering
Project Scope:
The Illinois Medical District station on the Forest Park branch of the CTA Blue Line underwent major renovation to improve accessibility and better serve the medical district in Chicago's west loop. A new elevator was installed, and the main stationhouse at Ogden was re-built. In addition to accessibility upgrades, the station and platform received new lighting, new security cameras, and new CTA Bus and Train Tracker displays. The two auxiliary entrances, at Damen and Paulina, received new flooring, wall and ceiling finishes, along with updated fare equipment and customer assistant kiosks.
Total Project Budget:
$23,000,000.00
Project Delivery Method:
Design/Bid/Build
Prime/Subcontractor:
Subcontractor