Project Name:
CTA East Lake, Milwaukee and Illinois Substations
Start/Scheduled Date of Completion:
May 2017 - December 2019
SQN's Role on Project:
Field Engineering
Project Scope:
The traction power equipment at the East Lake, Milwaukee, and Illinois substations is being replaced with new equipment, which includes the transformers, rectifiers, the AC and DC switchgear, the DC Bus, and cables. The building envelopes at these three locations are being rehabilitated to include new roofing, masonry restoration, tuckpointing, bathroom upgrades, and structural modifications.
Total Project Budget:
$40,000,000.00
Project Delivery Method:
Design/Bid/Build
Prime/Subcontractor:
Subcontractor